Skip to content

Behind-the-meter power cost calculator

Estimate gas generation cost per MWh, compare it with a grid tariff and test the value of starting earlier. Every input is an editable assumption.

The open cost model

What does a megawatt-hour really cost behind the meter?

Fuel by heat rate, capex annualized over 15 years at 10%, O&M — against your grid tariff, and against the value of connecting earlier. Use illustrative scenarios or set your own assumptions.

1,600
9,500
4.00
10
90
65
20
20
20

All presets are illustrative assumptions, not measured facility economics or live market prices. The Abilene permit provides equipment context; it does not establish every slider value. Gas and grid inputs can be checked against EIA gas data and state industrial averages. Earlier-operation value uses revenue × your incremental contribution margin. Include all costs other than the separately modeled power premium in that margin to avoid double counting. Results exclude discounting, taxes and any costs you have not included.

FuelCapexO&MGrid tariff
Behind the meter$75/MWh (38 fuel + 27 capex + 10 O&M)
Grid$65/MWh
BTM premium
+$9.7/MWh
10-yr power premium, per MW
$0.76M
Earlier contribution, per MW
$6.67M
Default illustrative assumptions: $74.7/MWh generation cost. Adjust the inputs to compare your scenario.

What does gas generation cost per MWh?

At the default illustrative assumptions, the model returns $74.7/MWh: $38.0 fuel, $26.7 annualized capital and $10.0 O&M. That is $9.7/MWh above the selected $65 grid tariff. These numbers are an example, not a market quote, a facility estimate or a live energy price.

The model is a screening tool for an analyst, developer or supplier comparing alternatives. It does not establish project feasibility, bankable LCOE, reliable capacity or investment return. Compare costs at the same delivery point and use your contracted tariff and delivered gas price.

Revisit or share your assumptions

Change the controls, then use “Link to this scenario” below the results. The link includes all nine inputs and opens this calculator with those values. Bookmark it or copy its address.

Sensitivity: gas price and utilization

Fuel price and capacity factor can change the comparison without changing the equipment. This table holds capex at $1,600/kW, heat rate at 9,500 Btu/kWh, O&M at $10/MWh and capital recovery at 15 years / 10%. It uses the same calculation as the interactive tool.

Illustrative generation cost, $/MWh · columns are assumed capacity factors
Gas, $/MMBtu60% utilization75% utilization90% utilization
$2.00$69.0$61.0$55.7
$4.00$88.0$80.0$74.7
$6.00$107.0$99.0$93.7
$8.00$126.0$118.0$112.7

At this heat rate, another $1/MMBtu of gas adds $9.50/MWh to fuel cost. Lower utilization spreads the same annualized capital across fewer generated MWh. Utilization is not a guarantee of availability; it is an assumption about output over the modeled year.

The formula, with units

Fuel ($/MWh) = heat rate (Btu/kWh) ÷ 1,000 × gas ($/MMBtu)
CRF = r × (1 + r)n ÷ ((1 + r)n − 1)
Capital ($/MWh) = capex ($/kW) × 1,000 × CRF ÷ (8,760 × capacity factor)
Generation cost = fuel + capital + O&M
r = 10%; n = 15 years; capacity factor is a fraction

EIA defines heat rate as energy input per kWh generated. Match the fuel heating-value basis and gross/net output basis to your heat-rate input. The 1,000 conversion above accounts for kWh/MWh and Btu/MMBtu.

Power premium and earlier operation

The signed BTM premium is modeled generation cost minus grid tariff. The ten-year additional power-cost figure uses the positive part of that difference × 8,760 × capacity factor × 10, per MW. If generation is cheaper, additional cost is zero; the signed per-MWh result still shows the saving.

Earlier contribution per MW = months saved ÷ 12 × assumed annual compute revenue per MW × incremental contribution margin. Include all incremental costs except the separately modeled power premium in that margin. At zero margin or zero months saved, earlier contribution is zero. This is a separate, undiscounted scenario amount, not a payback calculation.

Costs and constraints to add before a project decision

The calculator does not estimate those items separately. Verify whether each is already in your inputs before adding it again. For project context, read the Abilene turbine permit breakdown and the capacity interpretation guide.

Input sources and reproducibility

EIA's Henry Hub series is a benchmark, not your delivered gas contract. State industrial electricity averages are not a site tariff. Defaults are illustrative, not fetched prices. The model source and scenario checks are public.