Texas behind-the-meter data center power projects

Start with the air record. Follow the equipment, the legal entity and the dates before treating a proposed campus as available power.

What is documented in Texas?

Start with the reviewed Abilene equipment dossier and 3 additional project research dossiers below. Crusoe Stargate Abilene is identified in the air record as Longhorn Data Center, operated by Abilene DC 1, LLC. Its January 2025 permit review specifies 360.5 MW on a permitted, site-rated basis. Current metered delivery to computing is not established.

The broader inventory below contains 32 Texas entries with 63.2 GW of reported capacity from a third-party snapshot dated April 30, 2026. It is a research starting list. The snapshot's project statuses and expected dates have not been reverified here.

BTW's published Texas dossiers · export Oct 28, 2026
FacilityDocumented equipmentEvidence boundary
Crusoe Stargate AbileneTaylor County · Crusoe / Lancium360.5 MWPermitted site ratingsTCEQ 177263 and O4721No current output measurement published

Three more Texas projects, with different power boundaries

These selected primary-source dossiers distinguish regulator evidence, developer reports and open questions. They are separate research coverage and add no MW to the reviewed facility fleet or historical inventory.

Sources checked October 27, 2026 · selected coverage, not a statewide census
ProjectCapacity boundaryEvidence basis
Fermi Project MatadorCarson~6,000 MW permitted project scope; 17 GW planned campusRegulator technical review and registry; operator commercial reports
Crusoe Armstrong County / GoodnightArmstrong265.5 MW Goodnight 1 wind rating; campus output unknownOperator construction report, PUCT applicant filing and TCEQ registry
Blue Energy / Crusoe Port of VictoriaCalhounUp to 1.5 GW proposed nuclear generationPort authority announcement and developer partnership announcement

Follow the source-linked change log, including Abilene's permit revision, or download the research records.

Abilene: a permit trail you can follow

The original registration technical review records an August 15, 2024 receipt date. The later modification was received January 11, 2025 and approved January 22. These are different milestones: the modification date is not the first filing date.

The 177263 modification technical review changes the fleet from six to five turbines of each model. Five LM2500 units at 34.1 MW and five Titan 350 units at 38 MW give 170.5 + 190 = 360.5 MW. The review describes onsite use for data centers and computing. The separate O4721 federal operating permit was issued January 16, 2026.

Crusoe's September 30, 2025 announcement establishes that the data center was live by that report. It does not establish the exact first day of BTM generation or measured power from every permitted unit.

Read the turbine-by-turbine permit breakdown or open the complete Abilene evidence dossier, including receipts and event dates.

Texas project pipeline: the dated announcement layer

This is the Texas subset of the Environmental Integrity Project inventory carried in BTW's open data. Names, technologies, status and expected years below are as reported on April 30, 2026, including entries whose expected dates may now have passed. They are not confirmations of present construction, equipment orders, permits or operation. Capacities can describe different project phases and boundaries.

Original EIP spreadsheet · Full dated JSON with per-entry provenance · Published facility evidence appears separately above.

Show all 32 historical Texas project entries
Historical third-party snapshot · Apr 30, 2026 · not a current operating fleet
Reported project / countyReported MWStatus at snapshotExpected operation at snapshot
Fermi America Project MatadorCarson County · Combined Cycle11,280ProposedQ2 2027
GW Ranch Energy CenterPecos County · Simple Cycle7,650ProposedQ2 2027
Nexus Data Center Hubbard Power PlantHill County · Internal Combustion Engine, Simple Cycle, Combined Cycle7,227Proposed2027
Texas Power Generation Hub (Nextera-Comstock Power Station)Anderson County · Combined Cycle, Simple Cycle5,200Proposed2028/2029/2031/2032
Chevron AI Data Center ProjectCounty not reported · Unknown5,000Proposed2027
FO Permian Partners Data Center ComplexMidland County · Unknown5,000Proposed2026
Kilby Power PlantReeves County · Combined Cycle, Simple Cycle2,869ProposedUnknown
VoltaGrid ABI-1 Electric Generating StationShackleford County · Internal Combustion Engine2,582ProposedQ2 2026
NRG Tolar Power CenterHood County · Combined Cycle2,014ProposedUnknown
Alpha Digital Campus Power PlantReeves County · Unknown2,000Proposed2027/2028
Crusoe-Blue Energy Data Center Power StationVictoria County · Unknown1,500Proposed2028
Longhorn Data Center Power PlantTaylor County · Simple Cycle1,398ProposedQ1 2027
CloudBurst Data Center Power PlantComal County · Unknown1,200ProposedQ4 2026
Texas Critical Data Centers Power PlantEctor County · Simple Cycle, Internal Combustion Engine1,000Proposed2026/2027
Pecos Power GenerationReeves County · Combined Cycle956Proposed2027
Goodnight Data Center Power PlantArmstrong County · Simple Cycle933ProposedQ2 2027
Featherwood Energies Pecos Power PlantReeves County · Simple Cycle931ProposedQ2 2027
MMEX Pecos Power PlantPecos County · Combined Cycle640ProposedUnknown
Verdant Power PlantAngelina County · Simple Cycle600Proposed2026
Rock House Draw Generating StationPecos County · Internal Combustion Engine576ProposedQ4 2025
Misae Wilson Power PlantWilson County · Internal Combustion Engine519ProposedQ2 2028
Pacifico Ft. Spunky Power PlantHood County · Simple Cycle473Proposed2028
Pampa Data Center Power PlantGray County · Simple Cycle400Proposed2026
McCloud Generation FacilityEl Paso County · Internal Combustion Engine366ProposedQ2 2027
Poolside Generating StationPecos County · Simple Cycle332Proposed2027/2028
Circe Energy Data Centers E. Monahans CampusWard County · Internal Combustion Engine160Proposed2027
VoltaGrid SAT-2 Power PlantBexar County · Internal Combustion Engine149ProposedQ4 2025
Lone Star ProjectGlasscock County · Unknown100ProposedUnknown
Xenergy Monahans Power PlantWard County · Internal Combustion Engine98ProposedUnknown
Data City Energy CenterWebb County · UnknownUnknownProposed2026
Mesones Data Center CampusWilliamson County · UnknownUnknownProposedUnknown
Tract Austin Power PlantCaldwell County · Combined CycleUnknownProposed2028

How to qualify a Texas project

  1. Match the legal entity and location. Marketing names can differ from the permit applicant. Abilene DC 1 / Longhorn is an example; a name match alone is insufficient.
  2. Identify the document stage. A filing, technical review, issued authorization and operating record answer different questions. Keep the first application and later amendments separate.
  3. Check the equipment boundary. Separate primary onsite gas generation, emergency backup and grid capacity. Track the phase, model, count, site rating and hours together.
  4. Check commercial relevance directly. A permit naming equipment is not evidence of an open procurement opportunity. Verify scope and participants before treating a project as a sales lead.

To model economics after establishing scope, use the gas generation cost calculator. Replace the illustrative assumptions with your project's fuel, utilization, installed cost and tariff inputs.

Coverage and source dates

Abilene primary-record review: October 27, 2026. Announcement snapshot: April 30, 2026. The public export date is not a claim that every entry was rechecked that day. See source coverage and retrieval limits. The original registration review is linked in the dossier's source receipts.