Fermi Project Matador: power and evidence

A private-grid campus with a roughly 6,000 MW gas-generation permit scope, a larger 17 GW development ambition and a separately defined first customer lease.

Texas project research · Source-linked changes

What is established?

Fermi America / Fermi Inc. · Carson County, Texas

~6,000 MW permitted project scope; 17 GW planned campus

Evidence basis: Regulator technical review and registry; operator commercial reports. Sources checked .

Project identity, phase and capacity boundaries
FieldSource-linked findingEvidence
Legal applicant and identityFermi Equipment Holdco, LLC; RN112258678; Carson CountyTCEQ construction-permit technical review, project 396274
Air authorization scope181009 / PSDTX1670 / GHGPSDTX254; approximately 6,000 MW nominal project generationTCEQ construction-permit technical review, project 396274
Turbines in the technical review90 Siemens SGT-800 combustion turbines, three GE Frame 6001/6B combustion turbines and 15 steam turbinesTCEQ construction-permit technical review, project 396274
Use of generated electricityOnsite hyperscale computing; technical review says no sale to the local utility distribution systemTCEQ construction-permit technical review, project 396274
First customer phase, as announced222 MW total facility power for TensorWave; phased delivery beginning in the second half of 2027Fermi announces TensorWave lease
Equipment arrival, as reportedThree GE Vernova 6B turbines arrived at the campus; operation is not established by arrivalFermi reports arrival of three GE Vernova 6B turbines

How to interpret the record

Matador is a project where the capacity boundary matters. The roughly 6,000 MW gas project in the TCEQ review and the operator's 17 GW campus plan describe different scopes. Neither is a measurement of electricity currently delivered to computing.

The review describes ninety 56 MW gross-nominal SGT-800 combustion turbines and three 45 MW gross-nominal GE 6B turbines, with steam generation in the combined-cycle configuration. Adding combustion-turbine ratings alone will not reproduce the whole-plant nominal figure. Keep the review's plant boundary with its number.

Fermi's first customer announcement gives a more specific commercial boundary: 222 MW of total facility power, with delivery beginning in the second half of 2027. Expansion rights beyond 650 MW are options. The announcement also states guaranty and financing conditions; these details matter when qualifying a delivery schedule.

What remains unknown?

  • Current net generation and delivered IT power
  • Commissioning and acceptance dates for each turbine block
  • Fulfilment of the lease's financing and guaranty conditions
  • Final scope and issuance of the separately listed East Campus applications

What to check next

  1. Track permit numbers and RN112258678 together; do not merge East Campus applications with issued authorizations.
  2. Look for commissioning or operating records after equipment-delivery reports.
  3. Compare future customer updates against the 222 MW phase and stated delivery conditions.

A documented project participant or equipment model is a research lead, not proof that procurement is open. Scope a monitoring pilot around the specific records and decisions you need.

Sources and dates

Reviewed sources are a dated selection, not a comprehensive search of every filing. Checking a page today does not make its older schedule or physical-status claims current. See automated source coverage.

Questions about this project

Is Matador operating at 17 GW?

The reviewed sources do not establish that. The 17 GW figure is the operator's development plan; the TCEQ review has a smaller gas-generation project scope.

Does arrival of a turbine establish available power?

No. The operator's arrival report is equipment evidence. Installation, commissioning and operation require separate records.